GYPSUM SET POINT ACCORDING TO SO3 REQUIERMENT

Previous Post
Next Post

GYPSUM SET POINT ACCORDING TO SO3 REQUIREMENT

 

 

SO3 REQUIREMENT = 1.8%

=(X – Y) / Z

X = REQUIRED % SO3 IN CEMENT (1.8%)

Y= SO3 % AGE IN CLINKER(0.4 TO 0.5%)

Z = SO3 %AGE IN GYPSUM   (41 TO 42 %)

X – Y / Z

=(1.8/100) – (0 .4/100 ) / 41 / 100

=( 0.018 – 0.004 / .41)*100

SET POINT =3.41

 

Previous Post
Next Post

1 thought on “GYPSUM SET POINT ACCORDING TO SO3 REQUIERMENT”

  1. Very useful website & happy to read the contents.
    Thanks for updating. Request you send the links in the below mail ID.

Leave a Comment

Your email address will not be published. Required fields are marked *

10 Essential Cement Plant Calculations

Free PDF — clinker chemistry, kiln sizing, ball mill power, and more. Enter your email and we'll send it immediately.

No spam. Unsubscribe anytime.

Check Your Inbox

Your PDF is on its way. Plus 6 more emails with cement plant tips and case studies.

Ask a Cement Engineer ×
Hello! Ask me any cement plant technical question — kiln, grinding, quality, maintenance, preheater. I'll give you a practical answer.