Cement mill audits

Cement mill audits Long & short term data analysis Production Operation Quality Evaluation & Potential estimation based on:-Comparison with other grinding systems -Theoretical calculations Short Term Data Analysis Operation Quality Targets of a “B” Level Audit Get to know well each of the circuit components Measuring is the base   Requirements for the “B” level […]

Continue reading

Chapter 4.2 Classifiers and Separators by Michael J. Knoflicek

Chapter 4.2 Classifiers and Separators by Michael J. Knoflicek Project Manager, Humboldt Wedag, Inc., Tel: (770) 810-7313, Email: mknoflicek@humboldt-wedag.com Due to the importance of the separation process to the energy efficiency of grinding systems and  to the quality of the product, a separate chapter has been devoted to this topic. Grinding and sepa- ration are […]

Continue reading

Chapter 4.1 Finish Milling and Grinding by Nile R. Strohman

Chapter 4.1 Finish Milling and Grinding by Nile R. Strohman Cement Additives, Grace Construction Products, W. R. Grace and Co. Conn., 11504 Long Meadow Drive, Glen Allen, Virginia 23059, 804-261-0761, nile.r.strohman@grace.com   The finish mill system in cement manufacturing is used for reducing the size of the clinker from as large as several centimeters in […]

Continue reading

Ball charge optimization

Ball charge optimization Date:              07.02.2002 Author(s):      Martin Rothfuchs, Marc        Brunelle, Wolfgang Stoiber, Didier Dumont last change by Martin Rothfuchs, 13.09.2001 15:38:23 Title: Ball charge optimization   Purpose Optimization of a ball charge for cement and raw mills with objective of optimizing the grinding efficiency.   Best Practice The ball charge in first and particularly in […]

Continue reading

Example Milling Problem: Low Mesh/High Blaine

Example Milling Problem: Low Mesh/High Blaine Cement At Plant A, the finish mill has been operating satisfactorily up until last weekend.  During the weekend, mill started backspilling forcing the shift crews to reduce feed rates by as much as 15%.  Curiously it was also reported that blaine rose from 370 to 410 (m2/kg) but the […]

Continue reading

Practical advanced & comprehensive guide for ball mill design , operation & maintenance

advanced & comprehensive guide for ball mill design , operation & maintenance Mr Ortega   the source of the data : Lafarge ,  FLS guides , Holcim Guide , Duda data  cement book and other Engineers and of course Mr Ortega 1           FEED AND FEED SYSTEM 1.1         Feed Temperature   Plants with satellite coolers have high clinker […]

Continue reading

CEMENT GRINDING SYSTEMS

CEMENT GRINDING SYSTEMS This article is a part of ASEC ACADEMY training course INTRODUCTION   The final manufacturing stage at a cement plant is the grinding of cement clinker from the kiln, mixed with 4-5% gypsum and possible additives, into the final product, cement .   In a modern cement plant the total consumption of […]

Continue reading

MECHANICAL ELEMENTS OF TUBE MILLS

MECHANICAL ELEMENTS OF TUBE MILLS this is a part of ASEC Academy training Courses SUMMARY the mechanical elements of a tube mill could be separated into elements which have a direct function with the grinding process (i.e. grinding media, liners, diaphragms) and into elements which can be considered as individual units which are connected to each […]